The IMO net-zero framework is often discussed as if it were already part of a ship's certificates. It is not. It is the name commonly given to mid-term greenhouse gas measures that IMO member states have been developing under the 2023 IMO Strategy on Reduction of GHG Emissions from Ships. A draft was approved in April 2025. Formal adoption was not completed at an extraordinary session of the Marine Environment Protection Committee in October 2025, and the framework was still not in force after MEPC 84, held from 27 April to 1 May 2026. Further meetings were scheduled later in 2026. This article does not anticipate their outcome.
This is a practical briefing for operators, designated persons and masters. It separates what is already in force from what is still under negotiation, and it does not treat proposals as law. The official source for any later decision is the IMO text itself, not a trade commentary, and not this article.
What the IMO net-zero framework is, and what it is not
The 2023 IMO GHG Strategy, adopted at MEPC 80 on 7 July 2023, is the standing policy document. It sets an ambition to reach net-zero GHG emissions from international shipping by or around 2050, that is, close to 2050, taking into account different national circumstances. It also includes, compared with 2008:
- a level of ambition to reduce CO2 emissions per transport work, as an average across international shipping, by at least 40 per cent by 2030;
- an ambition that zero or near-zero GHG emission technologies, fuels and/or energy sources represent at least 5 per cent, striving for 10 per cent, of the energy used by international shipping by 2030; and
- indicative checkpoints to reduce total annual GHG emissions from international shipping by at least 20 per cent, striving for 30 per cent, by 2030, and by at least 70 per cent, striving for 80 per cent, by 2040.
The Strategy is to be kept under review, with a view to a revision in 2028. It is a strategy, not a set of shipboard certificates.
The mid-term measures intended to help deliver that strategy are what is usually meant by the net-zero framework. In the draft work, those measures have been discussed as including a greenhouse gas fuel-intensity standard and some form of economic or pricing element, as amendments to MARPOL Annex VI. Because the amendments have not been adopted, this article does not set out thresholds, dates of application, or payment figures as if they were requirements. Those details, if and when they exist in an adopted text, will come from IMO.
What is already in force for ships that fall under the current MARPOL Annex VI provisions includes the short-term technical and operational measures: the Energy Efficiency Existing Ship Index (EEXI), the Carbon Intensity Indicator (CII), the Ship Energy Efficiency Management Plan (SEEMP), and the IMO Data Collection System (DCS). Applicability, calculation methods and any exemptions should be taken from the ship's certificates and the current Annex VI text, not from a remembered summary.
What operators should do now
The practical duty has not changed because a later measure is under discussion. Keep the measures that already apply in date: EEXI technical files, CII and DCS reporting, and the SEEMP as required for the ship. If a voyage, a repair or a dry-docking will affect those documents, plan the paperwork with the work, not after it.
Fuel planning should be based on the rules that apply to the ship today, including any emission control area requirements on the intended voyage, and on what the bunkering ports can actually supply. Do not assume that a draft mid-term measure already dictates the fuel that must be stemmed in The Bahamas or South Florida.
Technical work that supports efficiency — hull condition, propeller work, machinery repairs — still has to be planned around a port call in the ordinary way. Marine Technical Services is relevant when that work is to be done in The Bahamas or South Florida, but it does not change the ship's statutory position. The FAQs set out the usual information to send with a call.
Watch official IMO circulars and the flag's instructions for any later decision. If a mid-term measure is adopted, the dates, the scope and the transitional arrangements will be in that text. Until then, a commercial presentation or a draft compromise should not be written into the SMS as if it were already mandatory.
Frequently asked questions
Is the IMO net-zero framework already a MARPOL requirement? No. A draft was approved in April 2025, but formal adoption was not completed in October 2025, and the framework was still not adopted after MEPC 84 in late April and early May 2026. Confirm any later change from official IMO texts.
Do EEXI, CII, SEEMP and the DCS still apply while mid-term measures are being negotiated? Yes, for ships that fall under the current Annex VI provisions. Those short-term measures are separate from the unadopted mid-term package.
Should we plan fuel and capital spending as if a particular draft threshold were already in force? Plan against the rules that apply now, and against what the company can reasonably see in official texts. Do not treat an unadopted threshold or pricing figure as a legal requirement.
A short closing note
This is an industry briefing, not legal advice and not a forecast of later IMO meetings. Russmill Maritime Services Limited is a ship supplier, service provider and port agent in The Bahamas and South Florida. For questions about an upcoming call, email ops@russmillmaritime.com or call +1 242 821 7780.